FEATURE ARTICLE, FEBRUARY 2005
Designing on Brownfields
Creative architecture is key to a successful brownfield
development.
Philip Daly
As open green land becomes harder and harder to come by in
many parts of the Northeast, developers are taking another
look at brownfields. Many of these sites are located in highly
desirable areas, and despite the challenges and risks of taking
them on, these sites can be lucrative investments.
An example of these challenges can be seen in the recent development
of a landfill site in eastern Massachusetts. The 33-acre former
town dump, located just off one of the areas busiest
highways, had been an eyesore, major liability and tax drain
for the town since it closed some 20 years ago.
Vendors were thrilled with the location and quality of the
development, the developer realized a good return on its investment,
and the town is receiving much-needed new tax revenue. But
make no mistake: Getting to a win-win situation on a brownfield
site is a challenge.
There are no set solutions for brownfield developments. Each
development is uniquely driven by the nature of the environment,
market and location. Frequently, former landfills are turned
into developments like parks, playing fields or golf courses.
In the case of the eastern Massachusetts development, the
location and high visibility justified a higher use for the
land. Because the site was a former landfill, most of the
buildings had to be supported on piles. Pile foundations are
expensive and introduce an element of risk, especially when
dealing with former landfills. For example, the contractor
may be driving a cluster of piles, get three in, and the fourth
might hit an old engine block and break, making it necessary
to redesign the whole cluster immediately. The developer in
this case minimized some of the risk through extensive test
drilling, pre-excavation and pre-augering. But you can never
eliminate all of the risk or the cost associated
with pile driving on a landfill.
Methane gas is a major issue that developers face when developing
on landfills. Sometimes the gas can be collected and turned
into a useful energy source. In the Massachusetts development,
studies indicated that there was insufficient gas for generating
electricity. Nevertheless, a gas collection system had to
be installed under the entire site and building. The gas is
drawn through a network of pipes to a flare station where
the gas is burned off. The gas collection system in turn created
a need to install a separate, sub-surface drainage system.
On top of these two systems, the developer had to install
an impermeable cap membrane that needed to be sealed as tight
as a roof covering. Any penetrations through the cap layer
had to be avoided or carefully detailed to maintain the seal.
These penetrations obviously included the foundation piles,
but also included a myriad of other items such as fence posts,
sign posts, light poles and pipe bollards, to name a few.
The cap layer also had to be contoured to provide corridors
for the site utilities and to drain to the site perimeter
without low spots. Only environmentally clean and certified
fill material could be installed above the cap layer. The
surface then had to be graded to meet all the surface drainage
and building access requirements of a normal building project.
While the project civil engineers and geotechnical consultants
were responsible for creating solutions to the problems already
mentioned, designing the actual buildings and amenities that
can be built on such a site posed a whole different set of
challenges for the architectural team. Because the site is
a former landfill, there is a high degree of anticipated settlement
as much as 24 inches in some areas. Since the building
is sitting on piles, it is not going anywhere. But sidewalks
leading into the buildings could settle, creating entry problems.
In some cases sidewalks were installed on piles with an additional
hinged slab to transition to the paved areas. In other areas,
the sidewalks were cantilevered off the building.
Utility connections coming into the building are also rigid
at the building line, but could settle where they run in the
site material. The high degree of anticipated settlement required
that each utility line had to be individually engineered with
expanding flex joints. Utility lines beneath the building
are suspended from the structural floor slab. Each hanger
penetrating the cap membrane had to be carefully sealed and
tested before the slab could be poured.
The nature of the site required that even the most mundane
construction details be re-examined. One small example was
the parking lot lighting poles. Placing these on pile supports
was not economically feasible but the size of footing required
to keep the poles from tipping over would have caused the
footings to sink under their own weight. We designed some
of the poles with hollow footings that would settle at the
same rate as the surrounding site.
Another problem was handling the surface drainage from the
parking areas. Due to the cap membrane there was little or
no permeable area. Typically, a site like this will include
a large retention pond to hold excess water from paved parking
areas. Retention ponds are usually open depressions. Instead,
one of the retention areas was located under the parking lot
while another is located under one of the buildings.
Another challenge of brownfield development is the lack of
precedent. Developing brownfield sites is still an evolving
science and since the problems are unique to each site, there
are few off-the-shelf solutions. But that is sure to change
as more developers are tempted to remediate and develop brownfield
sites.
Building on environmentally compromised land is not easy or
cheap, but as this project has shown, it can be done to everybodys
benefit. q
Philip Daly is an associate and architectural discipline
leader at Carter & Burgess in Boston. As architectural
discipline leader, Daly is responsible for providing technical
leadership and the development of the architectural department.
©2005 France Publications, Inc. Duplication
or reproduction of this article not permitted without authorization
from France Publications, Inc. For information on reprints
of this article contact Barbara
Sherer at (630) 554-6054.
|